Setting the Fibre Channel topology

Procedure

  1. Open the Ports/Host Groups/iSCSI Targets window.

In Command Suite:

  1. On the Resources tab, click Storage Systems, and then expand All Storage Systems and the target storage system.

  1. Click Ports/Host Groups/iSCSI Targets.

In Device Manager - Storage Navigator:

  1. Click Storage Systems, and then expand the Storage Systems tree.

  1. Click Ports/Host Groups/iSCSI Targets.

  1. In the Ports/Host Groups/iSCSI Targets window, click the Ports tab.

  1. Select the desired port, and then click Edit Ports.

  1. Under Connection Type, select FC-AL or P-to-P.

  1. Click Finish.

The Confirm window opens.

  1. In the Task Name text box, type a unique name for the task or accept the default.

You can enter up to 32 ASCII characters and symbols, with the exception of: \ / : , ; * ? " < > |. The value <date>-<window name> is entered by default.

  1. Click Apply.