Services are migrated from the production center to the DR center due to a recoverable fault such as an unexpected power failure. After the production center recovers from the fault, you must synchronize data generated during the fault recovery period from the DR center to the production center and switch services back to the production center.
Ensure that the applications in the production center have been stopped before uninstalling disks.
Data needs to be copied from the DR center to the production center to complete the initial data synchronization.
If Save user configuration data is selected, self-defined protection policies and recovery settings, such as self-defined recovery steps, will be retained. Ensure that the configuration data has no adverse impact on service running after reprotection.
Before the services are switched back, you need to perform a DR test to verify the data availability to ensure that services can be successfully switched back. After the test, you must clear the test data to avoid switchback failure caused by test data. For details, see DR Testing in the DR Center.
This step aims to switch services back to the production center from the DR center. After migration, data must be checked and test data must be cleared. For details, see 2 to 4 in Planned Migration of Services in the Production Center.
Copy data from the production center to the DR center to recover the protected group status.