This section describes how to perform planned service migration from the production center to the remote DR center on cascading and parallel networks.
If no DR test is performed before the planned migration, the migration has a higher rate to fail. A migration failure will interrupt DR services. For this reason, at least one recovery plan test must be executed successfully before the planned migration.
After services in the production center are migrated to the remote DR center in a planned manner, protected groups become invalid. You need to manually configure the protected groups after services are migrated back to the production centers.
Migrate services in the production center to the remote DR center. After the migration, test data and clear the data generated during tests. For details, see Step 1 to Step 4 in Planned Migration from the Production Center to the Same-City DR Center.
After the planned migration is performed: