DR Testing

This section describes how to test data in the remote DR center. DR tests are implemented by snapshot mappings at the DR site to verify the availability of data or snapshots replicated to the DR center. The test process has no adverse impact on the production site. After a test is complete, the test data generated at the DR site needs to be cleared and resources need to be restored to the status before the test to facilitate future DR or planned migration.

Prerequisites

Context

Data test in the DR center is used to verify data availability. You are advised to configure application-based protection policies to support tests by one click.

In a DR test, snapshots at the DR site can only be mapped to the initiators. The port mapping mode is not supported.

Procedure

  1. Log in to Fibre Channel switches one by one, check the information about each Fibre Channel port, and calculate the BER. If the BER is larger than 0.1%, check links and rectify link faults.

    BER = Total number of errors/(In bytes + Out bytes) x 100%

    A large BER may result in a remote replication failure in a specified window or an unexpected remote replication disconnection.

  2. Log in to the UltraVR DR management server in the remote DR center.
  3. Test a recovery plan.

    1. On the menu bar, select Recovery.
    2. Select the recovery plan to be tested, and click Test on the Operation list.

      If Huawei UltraPath has been installed on the Linux-based DR host, ensure that I/O suspension time is not 0 and all virtual devices generated by UltraPath have corresponding physical devices. For details, see the OceanStor UltraPath for Linux V100R008C00 User Guide.

    1. Select a test network.

      The default test network is the network for resource mapping. If you want to change the default network, plan or select another network based on site requirements.

    2. Click Test.

  4. After the test is complete, verify that applications are started in the remote DR center.

    Verify that applications are started and accessed successfully. If an application fails to be started or cannot execute read and write operations, contact Huawei technical support.

  5. The test data generated at the DR site needs to be cleared and resources need to be restored to the status before the test to facilitate future DR or planned migration.

    • If the protected groups are FusionCompute VMs and deleting storage fails during test data clearing, check whether non-DR VMs or disks exist on the datastore. If non-DR VMs or disks exist, migrate or delete them from the datastore.
    • If the information about storage devices or FusionCompute VMs is modified at the production or DR site, manually refresh the information. For details, see Refreshing Resource Information.
    1. Select the recovery plan whose data needs to be cleared, and click More > Clear on the Operation list.
    2. Click OK.