DR Testing in the DR Center

This section describes how to test data in the DR center. DR tests are implemented by snapshot mapping at the DR center to verify the availability of data or snapshots replicated to the DR center. The test process has no adverse impact on the production site. After a test is complete, the test data generated at the DR site needs to be cleared and resources need to be restored to the status before the test to facilitate future DR or planned migration.

Prerequisites

Context

Due to the importance of DR tests, notify the following:

  • During a DR test, system and service administrators are not allowed to perform any maintenance operation.
  • Test data must be cleared before the next DR test.
  • After a test is complete, test data must be cleared as soon as possible. If the environment is recovered after a network failure or UltraVR environment shutdown during the test, performing clearing may leave some data. In this case, you must manually clear the test data, then perform clearing again.

Procedure

  1. Log in to UltraVR in the DR center.
  2. Test a recovery plan.

    1. On the menu bar, select Recovery.
    2. Select the recovery plan to be tested, and click Test on the Operation list.

      If Huawei UltraPath has been installed on the Linux-based DR host, ensure that I/O suspension time is not 0 and all virtual devices generated by UltraPath have corresponding physical devices. For details, see the OceanStor UltraPath for Linux V100R008C00 User Guide.

    3. Select a test network.

      The default test network is the network for resource mapping. If you want to change the default network, plan or select another network based on site requirements.

    4. Click Test.

  3. After the test is complete, verify that applications are started in the remote DR center.

    Verify that applications are started and accessed successfully. If an application fails to be started or cannot execute read and write operations, contact Huawei technical support.

  4. The test data generated at the DR site needs to be cleared and resources need to be restored to the status before the test to facilitate future DR or planned migration.

    • If the protected groups are FusionCompute VMs and deleting storage fails during test data clearing, check whether non-DR VMs or disks exist on the datastore. If non-DR VMs or disks exist, migrate or delete them from the datastore.
    • If the information about storage devices or FusionCompute VMs is modified at the production or DR site, manually refresh the information. For details, see Refreshing Resource Information.
    1. Select the recovery plan whose data needs to be cleared, and click More > Clear on the Operation list.
    2. Click OK.