Starting a Pull Task

This section describes how to start a pull task.

Prerequisites

This operation is not supported for tasks in the Synchronizing data or To be scheduled status.

Procedure

  1. Choose Resources > Dataflow > SmartSync > Pull Tasks.
  2. Select a desired account from the Account drop-down list in the upper left corner.
  3. Select desired pull tasks from the list, click Operation above the list, and select Start. You can also click More on the right of a desired pull task in the list and choose Start.

    If the status of a task is Faulty, the task will be executed again after being started. If the status of a task is Paused, the task will resume from the breakpoint after being started.

  4. Confirm your operation as prompted.