Predefined setup checklist for model 9111-285 with logical partitions

If you plan to configure logical partitions, use the Integrated Virtualization Manager, set up the Hardware Management Console (HMC), or install the HMC into a rack, then use this checklist to help you set up your system.

If you need help setting up the HMC, contact your next level of support or your hardware service provider.

For a successful installation, complete the following tasks in order.

Before you begin
__

Good planning is essential for the successful setup and use of your server. The customized Planning Checklist provides you with the planning tasks you need to perform. Have you completed the Planning Checklist?

__

Ensure that you have completed the tasks from the Quick start guide for IntelliStation® POWER™ 285Link to PDF that came with your server.

 

If you have not completed these tasks, links to this information are also available below.

After you finish
__

(Optional) Complete additional setup tasks.


Send feedback | Rate this page