PWR1920

Use this procedure to verify that the lights on the server control panel and the display panel on all attached I/O expansion units are operating correctly.

Please see Power isolation procedures for important safety information before continuing with this procedure.

Refer to Locating FRUs for instructions for removing and replacing any FRUs called out by the following procedure.

  1. Activate the Lamp Test by performing ONE of the following:
  2. Review the server control panel and the display panels on all attached I/O towers. The lamp test is only active on the I/O towers for 25 seconds after you press Enter. Check the following lights on at the control panel and all attached enclosures: Are all lights on at the control panel and all attached I/O enclosures?
  3. Are any abnormal characters or character patterns (not reference codes or normal display mode) displayed?
  4. Verify that all cables are seated correctly. If the problem persists, replace the control panel. If the problem still persists, use the following table to determine the possible causes for the Lamp Test failure:
    Table 33. Failing unit
    Failing unit FRU
    HV8 System backplane
    5088, 0588 Tower backplane assembly
    5094, 5294, 8094-002 Tower backplane assembly
    5095, 0595 Tower backplane assembly
    7311-D11, 7314-G30, 5790 or 5796 I/O backplane
    7311-D20 I/O backplane