You must connect the redundant ac-power switch to
the site power before you test the redundant ac-power switch.
Perform the following
steps to connect the redundant ac-power switch to
the site power:
- Determine a suitable cable
route from the redundant ac-power switch to
the power distribution units.
- Route the main input-power cable of
the redundant ac-power switch to
the specified power distribution unit,
and connect it.
- Route the backup input-power cable of
the redundant ac-power switch to
the specified power distribution unit,
and connect it.
- Verify that the redundant ac-power switch power
cables are tidy. Ensure that they do not obstruct other
equipment
and that they are tied in place where necessary.