Installing the support rails for the SAN Volume Controller 2145-8G4

You must install the support rails that hold the SAN Volume Controller 2145-8G4.

When you are ready to install the support rails, use the customer's hardware-location chart and the Electronic Industries Alliance (EIA) positions on the rack to determine where in the rack that the SAN Volume Controller node is to be installed.

Perform the following steps to install the support rails (shown in Figure 1) for the SAN Volume Controller 2145-8G4:
  1. Make sure you have all the items that you need for installing the support rails.
    Figure 1. SAN Volume Controller 2145-8G4 support rails installation kit
    This figure shows the support rails installation kit for the SAN Volume Controller 2145-8G4 node
    • Reference key one Rear of rail
    • Reference key two Rack mounting rails
    • Reference key three M6 screws
    • Reference key four Latches
    • Reference key five Front of rail
    Note: You might find it helpful, with some types of racks, to remove the rack doors and side panels to provide easier access during installation.
  2. Check the labels on the support rails. Each rail has a label that indicates which is the front end of the rail and whether the rail is for the left or right side of the rack. Perform this procedure for both rails.
  3. Insert the right slide rail number two into the rear rack mounting flange, as shown in Figure 2, with the rail pins number one protruding through the flange.
    Figure 2. Inserting the right slide rail into the rear rack mounting flange
    This figure shows how to insert the right slide rail
  4. Extend the right slide rail number two and insert it into the front rack mounting flange, as shown in Figure 3, with the rail pins number one protruding through the flange. Insert the left slide rail in the same way.
    Figure 3. Extending the right slide rail
    This figure shows how to extend the right slide rail
  5. Attach one latch strike number one to the front of the right rail number two, as shown in Figure 4, using the captive screw number three. Turn the screw only finger tight. Attach the other latch strike to the front of the left rail in the same way.
    Figure 4. Attaching the latch strike to the front of the slide rail
    This figure shows the captive screw and latch strike used to fasten the front of the slide rail to the rack
  6. Attach the slide rail to the left rear mounting flange with a single screw and latch strike. The screw should be only finger tight. Likewise, attach the other slide rail to the right rear mounting flange. The installation of the support rails for the SAN Volume Controller 2145-8G4 is complete.