Installing the support rails for a 2145 UPS

You must install the support rails in the rack before installing the 2145 UPS.

Before you install the support rails, determine where the 2145 UPS units are to be installed in the rack. Complete the following prerequisites before you install the support rails:
Note: The user can already have installed in the rack a 2145 UPS with available spare capacity. Therefore, the SAN Volume Controller 2145-4F2 might be delivered without a 2145 UPS.
Perform the following steps for each rail:
  1. Attach nut clips number four to the rack (see Figure 1). These nut clips must align with the second and fourth holes of the support rail flange.
    Figure 1. Support rail components for placing the 2145 UPS in the rack
    This figure shows the components for the support rails that are used to place the 2145 UPS in the rack
  2. Loosen the two wing nuts number two.
  3. Loosen the wing nut number three and slide the bracket toward the back of the rail.
  4. Remain at the back of the rack holding the support rail in position in the rack, and then install and fully tighten the two mounting screws number five.
  5. Go to the front of the rack.
  6. Extend the support rail toward the front of the rack.
    Note: Hold the support rail in position until you have completed step 8.
  7. Ensure that the support rail is horizontal (a level might be useful here).
  8. Install the two mounting screws number one into the third and fourth holes of the support rail flange. Fully tighten the screws.
  9. Fully tighten the two wing nuts number two.
  10. Loosen the wing nut number three and slide the bracket toward the front of the rail as far as it will go, with the front edge of the bracket against the back-end of the front support rail.
  11. Fully tighten the wing nut number three.
    Note: You must perform all of the previous steps for each rail.