Preparing for the SAN Volume Controller 2145-8A4 hardware installation

There are several steps that you must perform to prepare for the installation of the optional redundant ac-power switch, the uninterruptible power supply, and the SAN Volume Controller.

Figure 1 illustrates the major hardware components that you need.
Figure 1. Parts provided for SAN Volume Controller 2145-8A4 hardware installation in a rack
Items for installing SAN Volume Controller 2145-8A4 hardware in the rack

Two 2145 UPS-1U input-power cables, which are not shown in Figure 1, are also provided. One cable comes with the 2145 UPS-1U; it has an IEC 320-C14 plug, which is suitable for most rack-mounted power distribution units. The other country-specific cable comes with the SAN Volume Controller node; this cable is intended for use with your country-specific power sockets. You will use only one of these cables.

Before you start the installation, verify that all the parts that were ordered have been received and that all the component assemblies are complete. Ensure that you know the quantity of nodes and optional features that were ordered.

Three boxes are shipped for each node: one box contains the uninterruptible power supply, one box contains the publications, and the third box contains all the other parts. A label on the third, or main, box indicates the features that were shipped.

Note:
  1. You must install at least two SAN Volume Controller nodes. Each node requires an uninterruptible power supply.
  2. Optionally, install two redundant ac-power switches to power the nodes in an I/O group through two 2145 UPS-1U units.
  3. You must ensure that you have the appropriate cables to connect the redundant ac-power switch or uninterruptible power supply to the power distribution unit. See Redundant ac-power environment requirements and Power cables for the 2145 UPS-1U for more details.

Perform the following steps to prepare for installation:

  1. Ensure that you have everything you need for installation, including the customer-completed planning tables and charts. The customer can obtain the planning tables and charts from www.ibm.com/storage/support/2145.

    The IBM System Storage SAN Volume Controller Planning Guide provides guidelines for completing the planning tables and charts. These tables include the location of hardware, cable connection, and configuration data information that you need to complete the installation procedures. If you are connecting cables to switches that are currently in use, confirm with the customer that it is safe for you to proceed. Go no further with these instructions until you are satisfied that all the information is correct and valid.

  2. The label on the main box that indicates the features that were shipped. Make sure that the contents and quantity match the order.
    The following types of feature codes are included:
    • Feature code 0010: initial SAN Volume Controller 2145-8A4 software preloaded on feature code 3001 and 3002
    • One of the following:
      • Feature code 3001: initial SAN Volume Controller 2145-8A4 node, quantity 1
      • Feature code 3002: additional SAN Volume Controller 2145-8A4 node, quantity 1
    • One of the following country-specific SAN Volume Controller 2145-8A4 power cable feature codes: 9714, 9715, 9716, 9717, 9718, 9719, 9720, 9721, 9722, 9723, 9724, 9725, 9726, or 9727.
    • Feature code 8115: 2145 UPS-1U kit, quantity 1
    • Optionally, feature codes 5301 and 5325 for SAN Volume Controller fibre-optic cables, quantity 1 to 4
    • Optionally, feature codes 8300: redundant ac-power switch, quantity 1
  3. Check that the correct part set has been shipped for the feature codes. Unless otherwise stated, the feature code contents are in the main box.
    • Feature code 0010 is preinstalled software. There is no shipped part for this.
    • Feature codes 3001 and 3002 ship the same parts. Ensure that you have the following:
      • SAN Volume Controller 2145-8A4 node with Part number 32P9107 or Part number 46C7859
      • Part number 31P1197: SAN Volume Controller user publications and 31P1156: ship group in a separate box.
        31P1197 contains:
        • SAN Volume Controller Read first
        • IBM Systems Safety Notices
        • IBM System Storage SAN Volume Controller Model 2145-8A4 Hardware Installation Guide
        • IBM System Storage SAN Volume Controller Software Installation and Configuration Guide
        • IBM System Storage SAN Volume Controller Troubleshooting Guide
        • IBM System Storage SAN Volume Controller Hardware Maintenance Guide
        • SAN Volume Controller License information for IBM® CIM agent and console for SAN Volume Controller Console
        • SAN Volume Controller License information for SAN Volume Controller
        • SAN Volume Controller Statement of Limited Warranty
        • IPLA booklet for warranted products
        • ILA booklet with pointer sheet
        • IBM agreement for acquisition of support
        • IBM license information for machine code
        • Other miscellaneous flyers
      • 31P1156 contains:
        • Part number 31P1171: SAN Volume Controller power cable retention bracket, quantity 1
        • Part number 31P1177: Kit containing the power and signal cable bundle, quantity 1
      • The support rail kit contains a number of components within its box. Ensure that you have the following items:
        • One left side rail
        • One right side rail
        • Six M6 screws in a plastic bag
    • Feature codes 9714, 9715, 9716, 9717, 9718, 9719, 9720, 9721, 9722, 9723, 9724, 9725, 9726, 9727 each ship a single power cable. The power plug should be appropriate for your location unless you are connecting to a rack-mounted power distribution unit.
    • Feature code 8115 ships in a separate box that is labeled Part number 31P0874. Ensure that this box contains the following items:
      • 2145 UPS-1U, quantity 1
      • 2145 UPS-1U output power-cable retention-bracket kit, quantity 1
      • Uninterruptible power supply rail kit, quantity 1
      • Power cable for connection of the uninterruptible power supply to a rack PDU, quantity 1
      • Multilingual battery reconnection flyer and other miscellaneous flyers
    • Optional feature codes 5305 and 5325, the fibre-channel cables are shipped in plastic bags (one cable in each bag) and are labeled Part number 12R9914 and Part number 12R9915
    • Optional feature code 8300 ships in a box within the main box. Ensure that it contains the following items:
      • Part number 95P5083: redundant ac-power switch, quantity 1
      • Part number 31P0966: power cables, quantity 2
      • Part number 96P1728: mounting plates, quantity 2
      • Part number 12J5289: hex head screws, quantity 4
      • Part number 00N8709: "c" clips, quantity 4
      • Part number 24R0207: other screws, quantity 6
      • Part number 31P0876: label set, quantity 1

    If feature codes 5301 or 5325 were not ordered, the customer must supply the fibre-channel cables. Make sure that four cables per node are available.

    Note: Part numbers are subject to change between SAN Volume Controller releases. The part numbers listed here may not always reflect what the customer has received.
  4. Read the safety and environmental notices to ensure that you are correctly installing the 2145 UPS-1U units.
Library | Support | Terms of use | Feedback
© Copyright IBM Corporation 2003, 2009. All Rights Reserved.