Use the following information to replace the SAN Volume Controller 2145-8F4 or SAN Volume Controller 2145-8F2 service
controller.
To replace the service controller, perform the following
steps:
- Place the retention clip (
in Figure 1) over the locating
holes on the left side of the service controller. Figure 1. SAN Volume Controller 2145-8F2 or SAN Volume Controller 2145-8F4 service
controller
- Push the service controller into the cage until the retention
clip engages.
- Relocate the cage assembly and close the blue levers to
secure the cage assembly to the frame.
- Close the fan door (
in Figure 2) and replace
the node in the rack. Figure 2. SAN Volume Controller 2145-8F2 or SAN Volume Controller 2145-8F4 with
fan doors open
Note: The worldwide port names (WWPNs) of the fibre-channel
ports are derived from the worldwide node name (WWNN) of the service
controller. If you do not perform step
5, you might
have to re-zone the fibre-channel switches if the switch zoning uses
WWPN. You must restart the host systems before they are able to access
disks through this node.
- If you replaced the service controller
as part of concurrent maintenance, you must rewrite the WWNN on the
new service controller. If you do not, and the fibre-channel switch
zoning uses WWPNs, you cannot add the node back into the cluster until
the fibre-channel switches in the SAN are re-zoned. Also, the host
systems cannot access the fibre-channel ports on that node until the
host systems are rebooted.
To restore the WWNN, perform
the following steps:
- Determine the WWNN for the node by examining
the vital product data (VPD) of the node or the zoning that is defined
in the SAN switch. Record the last five numbers of the WWNN for the
node that you are working on.
- Start the node by performing a node rescue. See Performing the node rescue.
- Change the node WWNN by performing the following steps:
- On the front-panel display, press and release
the down button until the Node panel is displayed. Then press and
release the right button until the Node WWNN: panel is displayed.
- Press and hold the down
button, press and release the select button, and then release the
down button. The display switches into edit
mode. Edit WWNN is displayed on
line 1. Line 2 of the display shows the last five numbers of the WWNN
that is currently set. The first number is highlighted.
- Change the highlighted number to match the number
from the VPD or from customer zoning. Use
the up and down buttons to increase or decrease the numbers. The
numbers wrap F to 0 or 0 to F. Use the left and right buttons to move
between the numbers.
- When
the displayed value matches the numbers in the VPD or customer zoning,
press and release the select button to accept the numbers. The
Node WWNN: panel is displayed and the second line shows the last five
numbers of the restored WWNN.
Wait
one minute. If Cluster: is displayed
on the front panel, this indicates that the node is ready to be added
to the cluster. If Cluster: does
not display, see MAP 5000: Start to
determine how to solve this problem or contact the IBM® support
center.