The SAN Volume Controller 2145-CF8 uses
a cable-management arm to route and secure power cables and other
cables.
Replace the SAN Volume Controller 2145-CF8 cable-management
arm after you replace the node in the rack.
The cable-management arm is installed to pivot from the
left side of the SAN Volume Controller 2145-CF8 rack,
when viewed from the rear of the rack.
To attach the cable-management
arm, perform the following steps:
- At the rear of the rack, connect one end of the support
arm, as shown by 1 in Figure 1, to the
same slide rail to which you plan to attach the cable-management arm
so that you can swing the other end of the support arm 2 toward
the rack.
Figure 1. Rack rear:
Attaching the SAN Volume Controller 2145-CF8 cable-management
support arm
- Install the L-shaped cable-management stop bracket, as
shown by 1 in Figure 2 on the unattached
end of the support arm. Turn the bracket 2 to
secure it to the support arm.
Figure 2. Rack rear:
Installing the SAN Volume Controller 2145-CF8 cable-management
stop bracket
- To attach the other side of the support arm
to the backside of the slide rail, push the blue latch on the cable-support-arm
stop bracket, as shown by 1 in Figure 3, to slide
the bracket 2 into the slide rail.
Figure 3. Attaching
the free end of the SAN Volume Controller 2145-CF8 support
arm
- To install the cable-management arm assembly,
you must place the cable-management arm mounting bracket into the
same slide rail onto which you installed the cable-management support
arm.
The cable-management support arm is not shown
in Figure 4.
Push
the blue latch on the cable-support-arm stop bracket 1 to
slide the mounting bracket 2 into the
left slide rail. Push the bracket into the slide rail until the bracket
snaps into place.
Figure 4. Rack rear:
Installing the SAN Volume Controller 2145-CF8 cable-management
arm mounting bracket
- Place the cable-management arm on the support arm.
- Pull out the cable-management arm pin, as shown by 1 in Figure 5, then slide
the cable-management arm tab 2 into the
slot on the inside of the slide rail.
- Push the tab until it snaps into place.
- Pull out the other cable-management arm pin 3 ,
then slide the cable-management arm tab into the slot 4 on
the outside of the slide rail.
- Push the tab until it snaps into place.
Figure 5. SAN Volume Controller 2145-CF8 cable-management
arm on the support arm
- Attach the power cords and data cables to
the rear of the node.
- Route the cables and power cords on the cable-management
arm, as shown by 1 in Figure 6.
If
you attach the arm properly and route the cables properly, the arm
swings into the rack as you pull the node forward in the rack, opening
to allow the cables to follow the node toward the front of the rack.
You can perform some service procedures from the fully extended rail
position without disconnecting the fibre-channel cables and the Ethernet
cables. You can also perform some service procedures without turning
off the node or disconnecting the power cables.
- Secure the cables with cable ties or hook-and-loop fasteners.
Note: Leave some slack in all of the cables to avoid tension
in the cables as the cable-management arm moves.
Figure 6. SAN Volume Controller 2145-CF8 cables
in the cable-management arm
- Slide the SAN Volume Controller 2145-CF8 into
the rack until it snaps into place.
- Connect all cables to the back of the SAN Volume Controller 2145-CF8 node.