This topic describes how to replace the system-board SAN Volume Controller 2145-CF8 CMOS
battery.
DANGER
Multiple
power cords. The product might be equipped with multiple power cords.
To remove all hazardous voltages, disconnect all power
cords.
CAUTION:
The
battery contains lithium. To avoid possible explosion, do not burn
or charge the battery.
Do not:
- Throw or immerse into water
- Heat to more than 100°C (212°F)
- Repair or disassemble
Exchange only with the IBM-approved part. Recycle or discard
the battery as instructed by local regulations. In the United States,
IBM has a process for the collection of this battery. For information,
call 1-800-426-4333. Have the IBM part number for the battery unit
available when you call. (C003)
This service action assumes that:
- The node is turned off.
- The power cables are disconnected.
- The battery is removed from the node.
- The top cover is off.
Perform the following steps to replace the SAN Volume Controller 2145-CF8 system-board
CMOS battery:
- Follow any special handling and installation instructions
that come with the replacement battery.
- Locate the battery on the system board. Figure 1 shows the location
( 1 ) of the battery on the system board.
Figure 1. Location of the SAN Volume Controller 2145-CF8 CMOS
battery holder
- Insert the new battery:
- Tilt the battery so that you can insert it into the
socket on the side opposite the battery clip.
- Press the battery across into the socket
until it clicks into place. Make sure that the battery clip holds
the battery securely, as shown in Figure 2.
Figure 2. SAN Volume Controller 2145-CF8 CMOS
battery holder
- Make sure that all cables, adapters, and other components
are installed and seated correctly and that you have not left loose
tools or parts inside the node. Make sure that all internal cables
are correctly routed. If you disconnected the fibre-channel and Ethernet
cables, make sure that each cable is reconnected to the same port
from which it was removed.
- Replace
the top cover. See Replacing the top cover.
- If you removed the node from the rack, replace the node
in the rack, as described in Replacing the SAN Volume Controller in a rack.
- If you removed any fibre-channel or Ethernet cables,
use the labels you placed on each cable to replace all fibre-channel
and Ethernet cables in the same ports from which they were removed.
- If you removed
the power cords, replace the power cords and the cable-retention brackets,
as described in Replacing the cable-retention bracket.
- Lift the locking levers ( 1 in Figure 3)
on the slide rails and push the server 2 all
the way into the rack until it clicks into place.
Figure 3. Raising the SAN Volume Controller 2145-CF8 locking
levers of the slide rails of the rack
- Turn on the node.
- If there is a problem restarting the node, see MAP 5900: Hardware boot;
then connect a monitor and keyboard to the system and reset the BIOS
date and time.