Project 3.x: Cannot Level Tasks with a Rescheduled Duration
  
PSS ID Number: Q100510
Article last modified on 03-15-1995
 
3.00 3.00a | 3.00
 
WINDOWS    | MACINTOSH
 

------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 3.0, 3.0a
 - Microsoft Project for the Macintosh, version 3.0
------------------------------------------------------------
 
SUMMARY
=======
 
Page 219 of the "User's Reference" version 3.0, incorrectly states
that leveling can occur on tasks where the remaining duration has been
rescheduled.
 
Once a task has started (actual start date is set), the task can no
longer be leveled.
 
KBCategory: kbdocerr