Highlighted Tasks Takes Precedence Over Other Text Formats
  
PSS ID Number: Q105719
Article last modified on 03-15-1995
 
3.00 3.00a | 3.00
 
WINDOWS    | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 3.0, 3.0a
 - Microsoft Project for the Macintosh, version 3.0
--------------------------------------------------------------------
 
SUMMARY
=======
 
Tasks in the Task Sheet, Gantt Chart, and Task Report may appear with
the formatting of Highlighted Tasks if the All Tasks filter has been
applied with the Highlight option selected. The Highlighted Tasks
format is applied because the criteria is met by selecting all tasks.
 
Steps to Reproduce Behavior
---------------------------
 
1. From the View menu, choose Gantt Chart
 
2. From the Format menu, choose Text.
 
3. From the Item to Change list, select Critical Tasks.
 
4. Select the Bold check box.
 
5. Repeat steps 2 and 3 for Highlighted Tasks but select Italic
   instead of Bold and choose OK.
 
6. From the Filter menu, choose Define Filters.
 
7. From the list of Filters, select Critical.
 
8. Select the Highlight button in Define Filters.
 
The Critical tasks will appear in italics instead of bold and all
other tasks will be displayed according to their individual format.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 3.00 3.00a
=============================================================================