Project: Task Edit Form Creates Tasks on Blank Rows
  
PSS ID Number: Q108258
Article last modified on 03-15-1995
 
3.00 3.00a
 
WINDOWS
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 3.0, 3.0a, 4.0
 - Microsoft Project for Macintosh version 3.0
--------------------------------------------------------------------
 
SUMMARY
=======
 
If you use the Multiple Task Edit Form on a selection of tasks that
includes blank rows, the blank rows will become tasks with default
duration and schedule information.
 
To avoid creating tasks out of the blank rows, filter the project to
show only created tasks and then use the Multiple Task Edit form to
make your changes.
 
MORE INFORMATION
================
 
To create a task filter that will show only non-blank tasks in your
project, do the following:
 
1. From the Filter menu, choose Define Filters.
 
2. Choose the New button.
 
3. In the name field, type the name "Without Blank Rows" (without the
quotation marks).
 
4. Enter the following criteria for the filter:
 
      Field Name              Test            Value(s)
      ------------------------------------------------
 
      Unique ID            Gtr or Equal          1
 
5. Choose OK and then choose Set.
 
This will show a list of created tasks and will exclude blank lines
between tasks.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 4.00 3.00 3.00a
=============================================================================