Project: Valid Lead and Lag Values
  
PSS ID Number: Q109416
Article last modified on 03-15-1995
 
1.00 3.00 3.00a 4.00 | 1.10 3.00
 
WINDOWS              | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 1.0, 3.0, 3.0a, 4.0
 - Microsoft Project for the Macintosh, version 1.1 and 3.0
--------------------------------------------------------------------
 
SUMMARY
=======
 
The following is a list of valid time values that can be entered into the
Lag field in Microsoft Project. Lead and lag time can be expressed in
working time units or elapsed time units, or as a percentage or elapsed
percentage of the duration of the predecessor task.
 
   Working time          Elapsed time
   ----------------------------------------
   m=minutes             em=elapsed minutes
   h=hours               eh=elapsed hours
   d=days                ed=elapsed days
   w=weeks               ew=elapsed weeks
   %=%complete           e%=elapsed %complete
 
Lag time is created by using a positive time value from the above
list and lead time is created by using a minus sign before the time
value.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 4.00 1.00 1.10 3.00 3.00a M_PROJECT
=============================================================================