Dragged Gantt Bars Not Redrawn with Manual Calculation
  
PSS ID Number: Q114010
Article last modified on 09-18-1994
 
3.00 3.00a 4.00 | 3.00
 
WINDOWS         | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 3.0, 3.0a, 4.0
 - Microsoft Project for the Macintosh, version 3.0
--------------------------------------------------------------------
 
SUMMARY
=======
 
In Microsoft Project, when you are in the Gantt Chart view and you drag a
Gantt bar for a task that does not have an actual start date, the bar will
not be redrawn if the Calculation option is set to manual. However, the
bars will be redrawn when you recalculate the project.
 
MORE INFORMATION
================
 
Steps to Reproduce Behavior in Microsoft Project 3.0
----------------------------------------------------
 
1. From the Options menu, choose Calculation, select Manual, and choose OK.
 
2. On a Gantt Chart, enter a task.
 
3. Use the mouse pointer to drag the task to a new date.
 
The task won't move.
 
4. From the Options menu, choose Calculate Now.
 
The task is redrawn.
 
5. Enter 10% complete on the task.
 
6. Use the mouse pointer to drag the task to a new date.
 
The task will now move without calculating.
 
KBCategory: kbusage
KBSubcategory: kbtshoot
 
Additional reference words: 3.00 3.00a 4.00
 
=============================================================================