Project: Work Loaded at End on Successor in FF Relationship
  
PSS ID Number: Q119728
Article last modified on 11-07-1994
 
3.00 3.00a 4.00 | 3.00
 
WINDOWS         | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 3.0, 3.0a, 4.0
 - Microsoft Project for Macintosh, version 3.0
--------------------------------------------------------------------
 
SUMMARY
=======
 
Resource Work will be scheduled at the end of the task if the task has a
fixed duration and is the successor in a finish-to-finish (FF)
relationship.
 
MORE INFORMATION
================
 
Steps to Reproduce Behavior
---------------------------
 
1. In a Task Entry view, create 2 tasks with 5 days duration each, and link
   the tasks in a finish-to-finish relationship.
 
2. On the Gantt Chart, select task 2, and on the Task Form, mark the task
   fixed.
 
3. Assign a resource to task 2 with 8 hours work.
 
4. Change the lower pane to the Resource Usage view, and select task 2 on
   the Gantt Chart.
 
Note that the resource work will be assigned at the end of the task (this
is the expected behavior).
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 3.00 3.00a 4.00
=============================================================================
Copyright Microsoft Corporation 1994.