Project: Flag Field Documented Incorrectly in Online Help
  
PSS ID Number: Q122532
Article last modified on 04-06-1995
 
4.00    | 4.00
 
WINDOWS | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, version 4.0
 - Microsoft Project for the Macintosh, version 4.0
--------------------------------------------------------------------
 
Microsoft Project 4.0 Help describes how to use Flag task fields (Flag1,
Flag2, Flag3,...,Flag10) with the following statement:
 
   Use these fields to mark any task. They are used to roll up milestones
   on the Gantt bars. To mark a task, type yes in one of the flag fields.
   If you don't want a task marked, type no.
 
This information is incorrect. You cannot roll up milestones or mark a task
with a Flag field. To roll up tasks to a summary line, use the Rollup
task field. To mark tasks, use the Marked task field.
 
Note that Flag fields are most commonly used for filtering or for setting
up custom Gantt bars in the palette; Flag fields are not connected to any
specific task type.
 
KBCategory: kbdocerr kbusage
KBSubcategory:
=============================================================================
Copyright Microsoft Corporation 1995.