Prj4: No Left or Right Cursor Shape If Using Two Gantt Bars
  
PSS ID Number: Q124628
Article last modified on 05-17-1995
 
4.00    | 4.00
 
WINDOWS | MACINTOSH
 

---------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, version 4.0
 - Microsoft Project for the Macintosh, version 4.0
---------------------------------------------------------------------
 
SYMPTOMS
========
 
When you use two Gantt bars in the same row, and the Gantt bars have the
same start and finish dates, the left (%) and right (|->)cursor shapes may
be unavailable for the schedule bar (bar showing from Start to Finish).
 
WORKAROUND
==========
 
To work around this problem do either of the following:
 
 - Format the non-schedule bar (for example, a Baseline bar) so that it
   appears in row 2.
 
  -or-
 
 - Change the position of the bars in the Bar Styles dialog box so that
   the non-schedule bar is listed before the schedule bar.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 4.00 double
=============================================================================
Copyright Microsoft Corporation 1995.