PRJ4: Daily Recurring Task Allows Duration Greater Than One Day
  
PSS ID Number: Q131179
Article last modified on 06-14-1995
 
4.00    | 4.00
 
WINDOWS | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, version 4.0
 - Microsoft Project for the Macintosh, version 4.0
--------------------------------------------------------------------
 
When a daily recurring task is created, Microsoft Project allows a duration
of greater than one day. No error message is produced, and the tasks are
scheduled for the specified duration and they overlap.
 
The From and To dates affect only the start of an occurrence and how many
occurrences are generated; the duration is only a factor in how long a task
runs.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 4.00 alert illogical reschedule reocurring node
=============================================================================