PRJ4: Invalid Entry in Number Column Creates Task
  
PSS ID Number: Q131570
Article last modified on 08-24-1995
 
4.00    | 4.00
 
WINDOWS | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, versions 4.0
 - Microsoft Project for the Macintosh, versions 4.0
--------------------------------------------------------------------
 
SYMPTOMS
========
 
If an invalid entry is entered in a Number field on a blank task row,
Microsoft Project does not display an "Invalid Entry" message. Instead, the
Number field value is set to zero, and a task is created.
 
STATUS
======
 
Microsoft has confirmed this to be a problem in the products listed at the
beginning of this article. We are researching this problem and will post
more information here in the Microsoft Knowledge Base as it becomes
available.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 4.00 wrong error typo alphanumeric character
=============================================================================
Copyright Microsoft Corporation 1995.