PRJ4: Help Incorrect About SetSpecificTaskField/ResourceField
  
PSS ID Number: Q132872
Article last modified on 07-26-1995
 
4.00
 
WINDOWS
 

--------------------------------------------------------------------
The information in this article applies to:
 
 - Microsoft Project for Windows, version 4.0
--------------------------------------------------------------------
 
The Visual Basic Reference Help for Microsoft Project incorrectly
lists SetSpecificTaskField and SetSpecificResouceField as available
methods. These methods do not exist.
 
Instead of SetSpecificTaskField and SetSpecificResouceField, use the
SetTaskField and SetResourceField methods. The syntax and examples for
these methods in Microsoft Project's Visual Basic Reference Help are
correct.
 
KBCategory: kbprg kbdocerr
KBSubcategory:
 
Additional reference words: 4.00
=============================================================================