Recurring Task: Switching Length Reduces Number of Occurrences
  
PSS ID Number: Q136499
Article last modified on 09-26-1995
 
4.00    |  4.00
 
WINDOWS | MACINTOSH
 

--------------------------------------------------------------------
The information in this article applies to:
 
- Microsoft Project for Windows, version 4.0
- Microsoft Project for the Macintosh, version 4.0
--------------------------------------------------------------------
 
SYMPTOMS
========
 
The value in "For Occurrences" in the Recurring Task Information dialog box
may change when you switch to the "To" value.
 
CAUSE
=====
 
This behavior occurs when the "This Occurs-Daily" and the "Daily-Workday"
settings are selected in the Recurring Task Information dialog box and you
change the focus to and from the "To" and "For" boxes.
 
STATUS
======
 
Microsoft has confirmed this to be a problem in the products listed at the
beginning of this article. We are researching this problem and will post
new information here in the Microsoft Knowledge Base as it becomes
available.
 
KBCategory: kbusage
KBSubcategory:
 
Additional reference words: 4.00
=============================================================================