PRJ: Total Slack Calculated Incorrectly Using FF/SS Relationship |
Q107442
Total slack may not be calculated correctly when tasks are linked using a SS (start to start) or FF (finish to finish) relationship and may cause a task to show as non critical.
To work around this problem, change the FF relationship between T1 and T2 to FS (finish to Start) with a one day lead.