PRJ: Late Date Error Message Occurs with Single Task

Article ID: 108342

Article Last Modified on 1/18/2007


APPLIES TO


This article was previously published under Q108342

SUMMARY

When you enter an Actual Start date that is later than the Scheduled Start date and the task has a Must Finish On Constraint, you may receive the following error message:
Late Date before Start Date in Task X.
In Microsoft Project 98, a constraint indicator will be shown in the indicators field.

MORE INFORMATION

Steps to Reproduce Behavior

To create a situation in which you receive the error with only one task defined, do the following:

  1. Create a task with a 5 day duration and a constraint of Must Finish On.
  2. Set an actual start date for the task to a date after the Scheduled Start date (that is, if the Scheduled Start date is 12/1/93, make the Actual Start Date 12/3/93).
In Project 4.x: The error message 'Late Date Before Start Date in Task x' will be generated. This error message appears because the task cannot finish before the Constraint Date.

In Project 98: A constraint indicator will be shown in the indicators field.

Additional query words: 3.00a Negative slack

Keywords: kbinfo kbusage KB108342