Article ID: 112783
Article Last Modified on 11/25/2003
APPLIES TO
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 3.0a
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 3.0 for Macintosh
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q112783
SYMPTOMS
When you link projects in a master-subproject relationship and the master
and subproject use different calendars, the start date and the duration are
calculated from the master file's calendar, but the finish date is rolled
up from the subproject file's calendar.
CAUSE
These different calendars are used to ensure that the master project and
the subproject have the same start and finish dates.
REFERENCES
"User's Reference," version 3.0, pages 488-498
Additional query words: 3.00a
Keywords: kbprb KB112783