Task scheduled for nonworking time created as milestone
Article ID: 113154
Article Last Modified on 1/18/2007
APPLIES TO
- Microsoft Office Project Professional 2007
- Microsoft Office Project Standard 2007
- Microsoft Office Project Professional 2003
- Microsoft Office Project Standard 2003
- Microsoft Project 2002 Professional Edition
- Microsoft Project 2002 Standard Edition
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q113154
SYMPTOMS
In Microsoft Project, if you create a task by dragging on the Calendar or the Gantt Chart, and you start dragging on a nonworking day and stop dragging on a nonworking day, the task is created as a milestone.
WORKAROUND
To avoid creating a milestone task when you create a task by dragging on a
view, do either of the following:
MORE INFORMATION
PlanningWizards do not appear when you edit your project in the Calendar view. Because of this, when you format and edit your project in this view, you receive the same results as when you format and edit your project in the Gantt Chart view with the PlanningWizards turned off.
Additional query words: PRJ2002 PRJ2003 PRJ2007 prj2000 PRJ