Project: Duration Recalculated When Moving Task on Gantt Chart |
Q113364
kbusage
In Microsoft Project, when you drag a task on the Gantt Chart, and the task is 100-percent complete, the duration changes.
Note that this behavior also occurs when you change the Actual Start date for a task that has been completed. This behavior also affects Work and Cost information for the task.
If you want to move a completed task, or change the Actual Start date for a completed task without changing the duration, temporarily change the % Complete value to less than 100%. After you move the task, change the % Complete value back to 100%.
Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.
Additional query words: 3.00a
Keywords :
Issue type : kbbug
Technology :
|
Last Reviewed: November 3, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |