Summary Bar Not Displayed If Subordinate Is a Milestone |
Q113399
kbusageA Gantt Chart summary bar that has only a milestone as a subordinate will not display a bar.
A summary task shows a bar if the finish date is later than the start date. Since both the start date and finish date for a milestone are the same, the summary task can't display a bar.
Additional query words: 3.00a Disappears Zero Duration
Keywords :
Issue type : kbinfo
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject300Mac kbProject110Mac kbProject300 kbProject300a kbProject400 kbProject100
|
Last Reviewed: November 5, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |