Summary Bar Not Displayed If Subordinate Is a Milestone

Q113399

kbusage
The information in this article applies to:


SUMMARY

A Gantt Chart summary bar that has only a milestone as a subordinate will not display a bar.


MORE INFORMATION

A summary task shows a bar if the finish date is later than the start date. Since both the start date and finish date for a milestone are the same, the summary task can't display a bar.

Steps to Reproduce Behavior:

  1. Enter a task named Summary for Id 1.


  2. Enter a task named Task A with a duration of 0 days for Id 2.


  3. Make Task A a subordinate of Summary.


Note that there is no summary bar displayed for Summary.

Additional query words: 3.00a Disappears Zero Duration

Keywords :
Issue type : kbinfo
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject300Mac kbProject110Mac kbProject300 kbProject300a kbProject400 kbProject100


Last Reviewed: November 5, 2000