PRJ: Scheduling a Project Based on a Task Start Date
Article ID: 113447
Article Last Modified on 1/18/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.1a
- Microsoft Project 1.0 Standard Edition
- Microsoft Project 3.0 Standard Edition
- Microsoft Project 3.0a
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 1.1 for Macintosh
- Microsoft Project 3.0 for Macintosh
This article was previously published under Q113447
SUMMARY
If you want a project's start and finish dates to be calculated based on
the date for a particular task that occurs in the middle of the project
(for example, if you have a task that requires a delivery of material
before the task can begin, and you would like the entire project start and
finish dates to be calculated around this delivery date), you can do so by
manipulating the Schedule From option in the Project Info form.