Resource Work Not Calculated Correctly with Very Small Units |
Q113488
kbusageIn Microsoft Project, when you use very small units to indicate resource work, the work may be calculated incorrectly, the scheduled finish date may change, and you may receive an alert message that the resource is assigned outside of the dates for the task.
Microsoft Project stores all work, time, and duration in minutes. However, Microsoft Project sometimes has difficulty performing calculations at this level of precision.
1 day task = 480 minutesIf you assign .02 units of a resource to a fixed 1 day task, Microsoft Project calculates 9.6 minutes, or approximately 10 minutes of work. Microsoft Project rounds the 9.6 minutes to the nearest minute which equals 10 minutes.
duration = work/unitsIf you use the numbers from the above example in this equation, you get 10 minutes/.02 units, or 500 minutes; the resource needs 500 minutes to accomplish its total work of 10 minutes. But since the task is fixed at 480 minutes, the error message is generated because the resource needs to work 20 minutes later than the finish of the task.
Resource work for a fixed-duration task should be calculated based on the following formula
duration x unitsand the scheduled finish date for the resource should not change.
Additional query words:
Keywords :
Issue type : kbprb
Technology :
|
Last Reviewed: November 3, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |