SYMPTOMS
In Microsoft Project, when you use the
Send Task Request command to
send an electronic mail message to a resource assigned to your project, and you choose not to update the project file when you receive the reply from the resource, the following symptoms occur:
- When the resource receives your second message, the message does not
contain an Accept? column to either accept or reject the task
request.
- When you receive the second reply from the resource, the message
does not contain the Accept? column with the response of the
resource. Additionally, the message does not contain an Update Task
button.
- You no longer receive the message asking if you want to update the
Microsoft Project file when you reply to the message.
WORKAROUND
To avoid losing the Accept? column and the Update Response button in a Task Request mail message, choose the Update Response button in the message each time you receive a response from a resource, or choose Yes when prompted to update the project.
If you have already lost the Accept? column and the Update Response button in a Task Request mail message, you must open the project and send the task request to the resource again.
STATUS
Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
REFERENCES
For more information about the
Send Task Request Command, choose the
Search button in
Help and type:
Send Task Request command