PRJ4: Error Changing Units with 100 Resources Assigned |
Q113723
kbusageIn Microsoft Project, if you assign 100 resources to a task, and you then change the units of a resource assigned to the task using the Resource Assignment dialog box, you receive the following error message:
and the units assigned to the task are not changed.Too many resources assigned; only the first 100 will be used.
If you assign 100 resources to a task, to change the units of any resource assigned to that task, do any of the following:
-or-
-or-
Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.
Too many resources assigned; only the first 100 will be used.