PRJ4: Uncompleted Work Not Rescheduled on Project Update |
Q113755
In Microsoft Project, when you send a task Update Request message to a resource assigned to the task, uncompleted work is not rescheduled if no work has been completed by the resource.
This behavior occurs if the resource that is updating the task does not enter any value in the Work Completed field. If no work has been completed on the task, the task is not rescheduled with a later finish date.
To make sure that remaining work is rescheduled when you reply to an
Update Task Request message, do either of the following:
-or-
In Microsoft Project, when you enter a date in the Reschedule Uncompleted Work To Start box in the Update Project dialog box, if a task does not have an Actual Start date, it is rescheduled to start on this date you entered, with a Start No Earlier Than (SNET) constraint. However, the Update Project button in the Update Request dialog box does not reschedule a task if no work has been completed on the task.
For more information about the Update Project Command or the Update Task Command, choose the Search button in Help and type:
tracking progress: updating