Knowledge Base

Incorrect Late Start and Late Finish dates when you move a task in Project

Article ID: 113759

Article Last Modified on 11/30/2006


APPLIES TO


This article was previously published under Q113759

SYMPTOMS

In Microsoft Project, when you move a task to start after the project finish date, the Late Start and Late Finish dates for the task are calculated incorrectly if the project is scheduled from the project finish date.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed in the "Applies to" section.

MORE INFORMATION

When you move a task to start after the project finish date, and the project is scheduled from the project finish date, the task is scheduled after the project finish. This behavior is expected. However, the Late Start and Late Finish dates for the task are the same as the scheduled start and finish. This behavior is incorrect because the task cannot start or finish after the project finishes; therefore, the task should appear with negative slack.

Note that this behavior does not occur in Microsoft Project version 3.0.

Additional query words: PRJ2002 PRJ2003 PRJ 2007 prj2000

Keywords: kbtshoot kbpending kbusage KB113759