Subproject File Assigned to a 100% Complete Task Not Updated |
Q113770
When a subproject file is assigned to a task that is 100-percent complete, the master task is not updated to reflect the subproject file's status.
Microsoft Project does not recalculate the status for a task that is 100- percent complete.
To work around this situation, set the percent complete for the subproject task in the master file to something less than 100%. Microsoft Project will recalculate the task and display the correct status for the subproject.
Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.
Additional query words: 3.00a zero 0 %
Keywords : kbusage
Issue type : kbbug