Project: How and Where Custom Options Are Stored |
Q113792
Microsoft Project 4.0 provides a number of options that affect the project working environment. You can set these options in the Options dialog box (from the Tools menu, choose Options). Many of these options are project specific, and are saved with an individual project file.
The Preferences dialog box in Microsoft Project 3.0 has been replaced with
the Options dialog box. The options available in this dialog box affect
either how Microsoft Project operates (for example, how it performs
calculations, scheduling, and so on) or how Microsoft Project information
is displayed.
Most of the options you set in the Options dialog box are saved in the
WINPROJ4.INI file (this file replaces the Microsoft Project 3.0 WINPROJ.INI
file). WINPROJ4.INI is located in your Windows directory.
Some of the entries in the WINPROJ4.INI file function as default values and
may be overridden by the options you set in an individual project. The
options that can now be saved in individual projects (such as Default Hours
Per Day, and Default Duration Type) are those that are most likely to vary
between projects.
The following tables indicate which options are saved only in the
WINPROJ4.INI file, and which are project-specific. (Remember that values
for the project-specific options are saved in the WINPROJ4.INI file as
well, but these values serve only as default values for new projects).
The following Options are saved only in the WINPROJ4.INI file and not
in individual projects:
Option Values Default Value
-----------------------------------------------------------------
Advice From Planning Wizard Yes/No Yes
Advice About Using Project Yes/No Yes
Advice About Errors Yes/No Yes
Advice About Scheduling Yes/No Yes
Show Tips at Startup Yes/No No
Show Welcome Dialog on Startup Yes/No Yes
Open Last File on Startup Yes/No No
Prompt For Summary Info Yes/No Yes
User Name Text From setup
Option Values Default Value
-----------------------------------------------------------------
Default View Any View Gantt Chart
Date Format Date 1/31/94
Show Status Bar Yes/No Yes
Show Entry Bar Yes/No Yes
Show Notes Indicator Yes/No Yes
Show OLE Links Indicators Yes/No Yes
Show Scroll Bars Yes/No Yes
Option Values Default Value
-----------------------------------------------------------------
Allow Cell Drag And Drop Yes/No Yes
Ask To Update Automatic Links Yes/No Yes
Copy Resource Usage Header Yes/No Yes
Move Selection After Enter Yes/No Yes
Option Values Default Value
-----------------------------------------------------------------
Calculation Automatic/Manual Automatic
Option Values Default Value
-----------------------------------------------------------------
Show Scheduling Messages Yes/No Yes
Option Values Default Value
-----------------------------------------------------------------
Week Starts On Sunday /Monday Mon (Intl) / Sun (US)
Fiscal Year Starts In All months January
Fields to Check Yes/No(field) Yes (all)
Ignore Words in UPPERCASE Yes/No Yes
Ignore Words with Numbers Yes/No Yes
Always Suggest Yes/No No
Suggest from User Dictionary Yes/No Yes
Option Values Default Value
------------------------------------------------------------------
Default Standard Rate Currency
Default Overtime Rate Currency
Automatically Add New Resources Yes/No No
Option Values Default Value
------------------------------------------------------------------
Currency Symbol 1-6 chars $ (US)
Currency Symbol Placement Left/rightsp/no sp Left, no space
Show Summary Tasks Yes/No Yes
Show Project Summary Task Yes/No No
Indent Name Yes/No Yes
Show Outline Number Yes/No No
Show Outline Symbol Yes/No No
Option Values Default Value
------------------------------------------------------------------
Autolink Inserted Yes/No Yes
Default Duration Resource/Fixed Resource Driven
New Tasks Start On Project Start/Current Date Project Start
Show Duration In Minutes, Hours, Days, Weeks Days
Show Work In Minutes, Hours, Days, Weeks Hours
Split In-Progress Tasks Yes/No Yes
Tasks Are Critical 0 - 9999 0
Updating Task Status Yes/No Yes
Option Values Default Value
------------------------------------------------------------------
Default Start Time Time 8:00 AM
Default End Time Time 5:00 PM
Hours Per Day 0-24 8.00 hrs
Hours Per Week 0-168 40.00 hrs
Selecting the Set As Default button in any of the Options tabs writes
the current option settings to the WINPROJ4.INI file, at which point
they become the new defaults.
Option Values Default Value
------------------------------------------------------------------
Auto Indent Yes/No Yes
Display Syntax Errors Yes/No Yes
Break on All Errors Yes/No No
Require Variable Declaration Yes/No No
Tab Width 1 - 40 4
International Settings Current/Default Current
Option Values Default Value
------------------------------------------------------------------
Font Name & Size Size and Name Courier New 10
Code Colors
Foreground & Background Colors