PRJ4: Multiple "Late Date Before Scheduled Date in Subproject" |
Q113802
In Microsoft Project, if you link a task that contains a subproject to a constrained task such that a scheduling conflict occurs, you receive the following error message every time you edit or enter a task in the subproject until you resolve the conflict:
Late date before scheduled date in subproject...
This problem occurs when a task that contains a subproject is linked to a successor task, such that it causes a conflict with the successor task's scheduled dates. This causes a "Late date before scheduled date in <successor task>" error message to occur. This error message appears only once. However, the "Late date before scheduled date in subproject..." error message appears each time you edit or add a task to the subproject while the main project file is open.
To avoid receiving this error message multiple times, correct the scheduling conflict that is causing the error.
Note that if you have the Planning Wizard options selected on the
General tab of the Options dialog box, the Planning Wizard message that appears gives you some options to correct the scheduling conflict.
Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.
For more information about resolving this error message, do the following:
Additional query words:
Keywords : kberrmsg
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400
|
Last Reviewed: November 5, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |