Article ID: 113966
Article Last Modified on 11/13/2003
APPLIES TO
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q113966
SYMPTOMS
In Microsoft Project, if a Gantt view includes a definition for a Free
Slack or Total Slack bar, and if a task has an elapsed duration, then its slack bar is drawn too long (for example, the default Standard calendar slack bar will be about three times longer than it should be).
CAUSE
If a task has an elapsed duration, the Free Slack and Total Slack are stored internally in elapsed minutes. When a slack bar is drawn, the slack value is misinterpreted as working minutes, and the end of the bar is determined using working time from the project calendar.
STATUS
Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Keywords: kbbug kbpending kbusage KB113966