PRJ4: Upgrading Questions and Answers for Project 4.0 |
Q113994
The information in this article applies to:
-
Microsoft Project for Windows, version 4.0
SUMMARY
This article contains upgrading questions and answers for Microsoft Project
for Windows, version 4.0.
MORE INFORMATION
- Q. What new features are included in Microsoft Project version
4.0 for Windows?
A. Some of the new features of Microsoft Project version 4.0
include the following:
- The ability to use electronic mail to distribute task
assignments and request task updates.
- The GanttChartWizard asks you how you want your Gantt chart
to look and applies the proper formatting automatically.
Like Microsoft Office, Microsoft Project 4.0 features
ToolTips, tabbed dialog boxes, shortcut menus, customizable
toolbars, and object linking and embedding (OLE) 2.0 support.
- New multiproject consolidation and improved multiproject
resource sharing make it easier to manage multiple projects
and balance resources. Additional database utility features
enable Microsoft Project 4.0 to store and retrieve project
data in Microsoft Access DBMS database files.
- The new crosstab reports provide task and resource
information over time with the associated assignment
information over time as well.
- Microsoft Project 4.0 also includes the Microsoft Visual
Basic Programming System, Applications Edition, the
shared macro language for Microsoft Office programs.
- Q. What are the minimum hardware and software requirements for
Microsoft Project version 4.0 for Windows?
A. To run Microsoft Project version 4.0, you need the following:
- An IBM PC/AT or compatible, or PS/2, with an 80386 or higher
processor
- A minimum of 4 megabytes (MB) of RAM
- A hard disk drive with 9 MB of available hard disk space
- MS-DOS or PC-DOS version 3.3 or later
- Microsoft Windows operating system version 3.1 or later,
Microsoft Windows for Workgroups version 3.1 or later, or
Microsoft Windows NT version 3.1 or later
- An IBM-compatible VGA, 8514/A, or Hercules graphics card
or other high-resolution graphics card compatible with
Windows version 3.1 or later
- A Microsoft Mouse or other mouse or pointing device
compatible with Windows version 3.1 or later
- A 5.25-inch or 3.5-inch high-density disk drive or a 3.5-
inch low-density disk drive
- A MAPI- or VIM-compliant mail system to use electronic-mail-
enabled features
- Q. Microsoft Project version 3.0 does not have custom calculated
fields that I could define. Has this changed in Microsoft
Project version 4.0?
A. Microsoft Project version 4.0 includes Microsoft Visual Basic
Programming System, Applications Edition. Using this powerful
programming language, you can create simple macros to calculate
custom data on a task-by-task basis. All you need to do is run
the macro each time you want to update the data. Using this
method, you can create a macro to calculate almost any value
you need and have it placed in a number field.
For example, the following macro subtracts the start date from
the finish date for each task in the active project and places
the result in the Number1 column for that task.
Sub Macro1()
Dim t As Object
On Error Resume Next
For Each t In ActiveProject.Tasks
t.Number1 = t.Finish - t.Start
Next t
On Error GoTo 0
End Sub
Microsoft provides programming examples for illustration only, without warranty either
expressed or implied, including, but not limited to, the implied warranties of
merchantability and/or fitness for a particular purpose. This article assumes
that you are familiar with the programming language being demonstrated and the
tools used to create and debug procedures. Microsoft support professionals can
help explain the functionality of a particular procedure, but they will not
modify these examples to provide added functionality or construct procedures to
meet your specific needs. If you have limited programming experience, you may
want to contact a Microsoft Certified Partner or the Microsoft fee-based
consulting line at (800) 936-5200. For more information about Microsoft Certified
Partners, please see the following page on the World Wide Web:
http://www.microsoft.com/partner/referral/
For more information about the support options available from Microsoft, please see the
following page on the World Wide Web:
http://support.microsoft.com/directory/overview.asp
- Q. Microsoft Project version 4.0 combines view, calendar, and
project information in a single file. How do I copy elements
from my Microsoft Project version 3.0 files (calendar, view,
and project) into a Microsoft Project version 4.0 file so that
I have the same information available in 4.0 that I had in 3.0?A. To combine a Microsoft Project version 3.0 calendar file, view
file, and project file, follow these steps:
- In Microsoft Project version 4.0, open your Microsoft
Project version 3.0 calendar file.
NOTE: In Microsoft Project version 3.0 for Windows, the
default calendar file is Calendar.mpc.
- On the View menu, click More Views, and then click Organizer.
Click the Calendars tab.
- In the Calendars Available In list on the left, click
GLOBAL.MPT. From the equivalent list on the right, click
the Microsoft Project 3.0 calendar file. In the list under
the Microsoft Project 3.0 calendar file name on the right,
select the calendars you want to copy. Click Copy. In the
Organizer dialog box, click Close. In the More Views dialog
box, click Close.
- In Microsoft Project version 4.0, open your Microsoft
Project version 3.0 view file.
NOTE: In Microsoft Project version 3.0 for Windows, the
default view file is View.mpv.
- On the View menu, click More Views, and then click Organizer.
Select the Views tab.
- In the Views Available In list on the left, click
GLOBAL.MPT. In the equivalent list on the right, click
the Microsoft Project 3.0 view file. In the list under the
Microsoft Project 3.0 view file name on the right, select the
views you want to copy. Click Copy. In the Organizer dialog
box, click Close. In the More Views dialog box, click Close.
- Open your Microsoft Project version 3.0 project files.
To transfer customized elements from your Microsoft Project
version 3.0 view and calendar files to your Microsoft Project
version 4.0 project file or Global.mpt file, follow these steps:
- On the View menu, click More Views, and then click Organizer
Select the appropriate tab for the element (view, table,
filter, report, or form) that you want to copy to another
project file.
- In the Available In list on the left, click the Microsoft
Project version 4.0 file to which you want to copy the
element, or click GLOBAL.MPT to copy the information to
your global file. In the equivalent list on the right,
click the file that contains the Microsoft Project version
3.0 custom element that you want to copy. In the list
under the Microsoft Project 3.0 file name, click the custom
element you want to copy. Click Copy.
NOTE: If you copy an element with the same name as an
element in the destination file, you will receive a message
asking if you want to replace the element in the destination
file or rename the element you are copying.
- In the Organizer dialog box, click Close. In the More Views
dialog box, click Close.
- Q. In Microsoft Excel versions 4.0 and 5.0 and in Microsoft Word
version 6.0, I can use the secondary mouse button to bring up
a shortcut menu. Does Microsoft Project 4.0 have any shortcut
menus?
A. In Microsoft Project version 4.0, you can use the secondary
mouse button to access the most commonly used commands in
almost any situation. The menu commands available depend on
where you click. To find out what shortcut menus are available,
try clicking the secondary mouse button when the mouse pointer
is on the toolbar, the timescale, the Gantt Chart, or the Gantt
bars; shortcut menus are available nearly everywhere you can
click.
- Q. In Microsoft Project 3.0, I use the Resource Assignment
dialog box to add resources to my tasks. This dialog box has
changed in Microsoft Project version 4.0. Is this dialog box
still the best way to add resources to a task?
A. Because of the changes in the Resource Assignment dialog box,
the dialog box is even easier to use for assigning resources to
tasks. For example, the dialog box remains open while you edit
your tasks in the Gantt Chart; therefore, the dialog box is
always available when you assign resources.
To assign resources using this dialog box, use any of the following
methods:
- To assign the resource full time to the task, select the
tasks in your schedule, select the resource in the dialog box,
and click Assign.
-or-
- To drag a resource to a task line to assign the resource,
select the resource you want to assign, then move your mouse
to the row header until the profile of a person is displayed
below the mouse pointer. Drag the resource to a task (not
the Gantt bar for the task), and release the mouse button.
The resource is assigned full time to the task.
-or-
- To assign a resource part time from this dialog box, select
the task or tasks to which you want to assign the resource.
In the Units column, type the partial unit. For example, to
assign the resource half time, type .5.