Project: Remaining Duration Hours Calculated Incorrectly |
Q114310
kbusageWhen you track progress in a project in which the Show Duration In field is set equal to hours, the project statistics for Remaining Duration and Current Schedule are not calculated correctly.
To work around this problem, change the Show Duration In option to days instead of hours (Microsoft Project will round off the number of hours correctly if they are displayed in days rather than hours).
Microsoft has confirmed this to be a problem in the Microsoft products listed at the beginning of this article.
Additional query words: 3.00a
Keywords :
Issue type : kbbug
Technology :
|
Last Reviewed: November 3, 2000 © 2001 Microsoft Corporation. All rights reserved. Terms of Use. |