Planned Resource Information May Not Roll Up Automatically

Q114660

FixList4.00 kbusage
The information in this article applies to:


SYMPTOMS

In Microsoft Project versions 1.0, 3.0, or 3.0a, planned information is rolled up from resource assignments whenever the planned information is changed. This rolled-up information includes having the most current planned information on the task level if the planned information changes on a resource assignment.

However, when a resource is removed from a task after the plan has been set, the planned information for the deleted resource is removed from the plan for the task. This behavior may lead to incorrect planned information.


STATUS

In Microsoft Project version 4.0 for Windows, this behavior has changed:

Microsoft Project version 4.0 for Windows no longer rolls up resource planned information automatically to the task level when planned information at the resource level is changed. The planned fields for a task are updated only when you choose the Save Baseline command (from the Tools menu, choose Tracking, and then choose Save Baseline); therefore, if resources are added to a task that should be included in the plan, you must choose the Save Baseline command.

NOTE: You can choose to update only a selection of tasks instead of the entire project.


MORE INFORMATION

For more information about this behavior, query on the following words in the Microsoft Knowledge Base:

planned and work and resource and reflect and cost

Additional query words: 3.00a rolled up roll

Keywords :
Issue type : kbprb
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProjectMacSearch kbProject300Mac kbProject110Mac kbProject300 kbProject300a kbProject400 kbProject100


Last Reviewed: November 5, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.