PRJ: How to Display Summary Tasks on the Calendar View
Article ID: 114783
Article Last Modified on 1/18/2007
APPLIES TO
- Microsoft Project 2000 Standard Edition
- Microsoft Project 98 Standard Edition
- Microsoft Project 4.1 Standard Edition
- Microsoft Project 4.0 Standard Edition
- Microsoft Project 4.0 for Macintosh
This article was previously published under Q114783
SUMMARY
When you display the Calendar view, Summary tasks are not shown by default. This article describes how to display Summary tasks in Calendar view.