Project: Timescale Off by One Week |
Q115241
In Microsoft Project, when you format the Gantt Chart timescale such that the weeks are displayed with the "Jan 31, '94" label, the timescale will start one week late.
To work around this problem, do the following to format your project so
that Monday is the first day of the week:
Microsoft has confirmed this to be a problem in the Microsoft products that are listed at the beginning of this article.
Additional query words: timescale wrong week
Keywords :
Issue type : kbbug
Technology : kbHWMAC kbOSMAC kbProjectSearch kbProject400Mac kbProjectMacSearch kbProject400
|