Article ID: 115242
Article Last Modified on 1/19/2007
ID Name Unique ID Outline Level
1 1 1 1
2 2 2 2
3 3 3 2
4 4 4 3
ID Name Unique ID Outline Level
1 a 1 1
2 b 2 2
3 c 3 2
4 d 4 3
5 aa 5 1
6 bb 6 1
ID Name Unique ID Outline Level 1 a 1 1 2 b 2 2 3 c 3 2 4 d 4 3 5 aa 5 3 6 bb 6 3In Microsoft Project version 3.0, task IDs 5 and 6 would be at outline level 1 (because this is the level they had in the original file). Microsoft Project version 4.0 uses its "smart insert" feature to indent the unmatched tasks (IDs 5 and 6) to at least the same level as the last task in the project.
mpx and merge and how
MPX
Additional query words: combine outline
Keywords: kbprb kbusage KB115242