How to Link a Milestone to Begin on the Next Working Day

Q118347


The information in this article applies to:


SUMMARY

When a milestone is linked in a finish-to-start relationship, its scheduled start date may be the same as the predecessor's scheduled finish date. This behavior will occur if the milestone task has a constraint of As Soon As Possible and the predecessor task does not allow lag time.


MORE INFORMATION

Because the duration of a milestone task is 0 (0d), the task can start on the end date of the predecessor task. To schedule a milestone to begin the next day, use a duration of 0ed (elapsed days), as in the following example:


   Predecessor   Finish             Milestone     Dur.   Start
   ---------------------------------------------------------------------
   Task1         7/15/94 5:00pm     Task2         0d     7/15/94 5:00pm
   Task1         7/15/94 5:00pm     Task2         0ed    7/16/94 8:00am
   Task1         7/15/94 4:59pm     Task2         0ed    7/15/94 4:59pm 
NOTE: This will work ONLY if the predecessor task's finish date is equal to a nonworking time.

Additional query words: 3.00a

Keywords :
Issue type : kbhowto
Technology :


Last Reviewed: November 3, 2000
© 2001 Microsoft Corporation. All rights reserved. Terms of Use.